Added dates for deliverables/sprints.
[staff/due1/sed-hs15-srs-purple.git] / src / site / apt / eval / sprints.apt
1 -----------
2 Sprint Plan
3 -----------
4 Eric Dubuis
5 --------------
6 October 11, 2015
7 --------------
8
9
10 Sprint Plan of Project Smart Reservation System
11
12 * Introduction
13
14 The goal of this project is to simulate the incremental, iterative,
15 and agile software development process SCRUM. It is incremental in the sense
16 that functionality (and, thus, business value) is provided in an
17 incremental manner. It is iterative in so far that many development
18 activities (use case modeling, design, coding, testing, documentation, ...)
19 occur repeatedly. It is agile such that changes in customer requirements
20 can be handled (rather) easily.
21
22
23 * Schedule of Sprints
24
25 The following sprints and deliverables are planned:
26
27 *-----------------------------------------------+---------------*-----------------*
28 | Sprint/Deliverable | Due date | Points |
29 *-----------------------------------------------+---------------*-----------------*
30 | Sprint 1/{{{./s1.html}Deliverable 1 (D1)}} | Oct. 16, 2015 | 5 |
31 *-----------------------------------------------+---------------*-----------------*
32 | Sprint 2/{{{./s2.html}Deliverable 2 (D2)}} | Nov. 6, 2015 | 15 |
33 *-----------------------------------------------+---------------*-----------------*
34 | Sprint 3/{{{./s3.html}Deliverable 3 (D3)}} | Nov. 27, 2015 | 15 |
35 *-----------------------------------------------+---------------*-----------------*
36 | Sprint 4/{{{./s4.html}Deliverable 4 (D4)}} | Dec. 18, 2015 | 15 |
37 *-----------------------------------------------:---------------*-----------------*
38 | Total | | 50 |
39 *-----------------------------------------------+---------------*-----------------*
40 Planning of sprints and deliverables.
41
42
43 [Note:] Each deadline is Friday evening. However, you can provide